View Discrete Date Range UPDATE

I have another suggestion for viewing large and complex timelines.

THE PROBLEM

While you’re currently able to specify the view level based on different timescales (week, day, month, quarter…) it still involves continuous scrolling which makes it difficult to get a sense of the scale of time and relationship between events.

MY CURRENT SOLUTION

I create a number of tabs and set the date range for each tab in years. This allows me to see events year by year. I know the event at the top left of the screen will be the first event of that year and the final event the last of the year.

POSSIBLE SOLUTION

An option to view specific time periods where the first event of that period begins at the top left and the last event at the right hand side.

One option could allow you to step forwards and backwards discretely. Another allowing continuous scroll but with each time period being clearly differentiated and the first event appearing at the top left of that period.

ATTACHMENTS

First image shows all events at the YEARS scale but it’s difficult to see how many years are involved and where each year begins and ends.

Second image also shows events at the YEARS scale however there is a break between each year and the first event of each year begins at the top of the screen. (Small glitch in the attached pic. The first event for the second period - 2022 - isnt at the top of that section, but should be)

Third image is similar to the second however only shows a single period with navigation buttons to step forwards and backwards.

Hi JustAlex,

Thanks for the detailed suggestion and for including the examples. I can see the use case you’re describing, particularly the benefit of being able to clearly distinguish individual periods while working within a large Timeline.

I’m going to raise this with our development team and also discuss whether there are any other existing approaches that may help with the workflow you’ve described.

I’ll follow up with you once we’ve had a chance to look at this in more detail and explore some of the available options.

Thanks again for taking the time to explain the idea so clearly.

Kind regards,
Riaan
Aeon Timeline Support

Hi JustAlex,

Thanks for your patience while we discussed this with the team.

For viewing individual years separately, the approach you’re already using - creating a separate Timeline View for each year - is currently the best option.

For your continuous Timeline, you could also use a repeating Calendar Marker to make the beginning of each year more visible.

To set this up:

  1. Click the Calendar Marker icon in the left-hand sidebar
  2. Click New Calendar Marker and enter a name
  3. In the Inspector, set the Color and Icon (optional)
  4. Tick Draw on Timeline
  5. Set the Start date to the beginning of the first year you want to mark.
  6. Tick Repeat and set the marker to repeat every 1 years.

This will add a marker at the beginning of each year across the Timeline:

One thing to be aware of is that Calendar Markers are shared across Timeline Views, so the marker lines will appear in all Timeline Views while Draw on Timeline is enabled. If you need a cleaner Timeline for something like printing or exporting, you can temporarily untick Draw on Timeline to hide the marker lines, then enable it again afterwards.

We can see the benefit of the additional options you’ve suggested. We’ve considered different ways of improving how periods of time can be viewed and navigated in Aeon Timeline, although we don’t have anything specific to announce at this stage. Your examples and use case will be useful as we continue those discussions.

Thanks again for the detailed feedback.

Best,
Riaan
Aeon Timeline Support